YKE delivered solar grid-connection cabinets and step-up substations for a 50MW rooftop solar project in Indonesia.
YKE prepared the PLN approval documentation package, supporting one-pass approval and successful grid connection.
Project Snapshot
- Country
- Indonesia
- Client Type
- Local new energy developer
- Application
- Solar grid-connection and step-up distribution
- Project Capacity
- 50MW rooftop solar project
- Standards
- IEC aligned with Indonesian grid-connection approval requirements
- Delivery Result
- Supported one-pass PLN approval and successful project grid connection
- Region
- Southeast Asia
- Related Product Lines
- New Energy Electrical, Prefabricated Substations
Project Background & Requirements
- Local new energy developer
- Solar grid-connection and step-up distribution
- 50MW rooftop solar project
- Project reference details shared after NDA
Supply Scope & Key Parameters
- 12 sets of solar grid-connection cabinets and 12 sets of step-up prefabricated substations
- 50MW rooftop solar 12 grid-connection cabinets 12 step-up prefabricated substations
Key Technology & Standards
- PLN-oriented documentation package and SNI-aligned approval support
- IEC aligned with Indonesian grid-connection approval requirements
Delivery Result
- Supported one-pass PLN approval and successful project grid connection
- Project reference details shared after NDA